Roads

Pass Road Upgrade Project

1 July 2025 - 30 June 2027

Council is currently planning upgrade works on Pass Road, Rokeby, between Glebe Hill Road and Connor Place. It is intended the upgrading work from Winterborne Road to Connor Place be undertaken in 2025-2026, subject to contractor availability, with these works to be followed by the upgrading work from Glebe Hill Road to Winterborne Road.

Council plans to improve and widen the road so that it is more suitable for the increased traffic and type of vehicles using the road. Additionally, a shared path is to be provided on the western side of Pass Road from Glebe Hill Road to Winterborne Road with allowance for a possible future shared path from Winterborne Road to Connor Place.

The road widening will also require the relocation of some underground services and overhead power lines and poles.

For additional information please contact council’s Project Manager Mark Painter on 03 6217 9734 or mpainter@ccc.tas.gov.au.

Hours of Disruption: Monday to Friday work hours

Disruption Type: Changed traffic conditions

Stormwater

Beach Street storm water upgrade project

28 January 2025 - 30 April 2025

January 2025 update – works recommence  

Work to complete the Beach Street stormwater project will soon begin, with the project expected to restart on Tuesday, 28 January 2025 and be completed by end of April 2025. 

The project was postposed in June 2024 due to the impact work would have on the Spotted Handfish spawning season.  

These construction works include the installation of a large-scale, permanent stormwater pipe at the end of Beach Street, through the sand dune and into the River Derwent. Once complete, the upgraded stormwater system will reduce the risk of flooding of the road and private properties during heavy rainfall events. 

To ensure community safety during the works, part of Bellerive Beach and the Clarence Foreshore Trail, as well as surrounding roads and carparks will be temporarily closed. 

Please see details of the closures below.: 

  •          Bellerive Beach will be closed at the area where works are being conducted – between the entrance west of Beach Street and the entrance at High Street. You will still be able to access the beach, however detours will be in place for the section where the works are conducted. 
  •          The Clarence Foreshore Trail will be closed to all users at the section at the end of Beach Street, signage will be in place to detour users via Luttrell Avenue.
  •          Beach Street will be temporarily closed between Church Street and Luttrell Avenue and Luttrell Avenue will be temporarily closed between Beach Street and Facy Street. Access will be available for local traffic only.

 Residents can also expect: 

  • reduced speed limits on local roads 
  • onstreet parking restrictions 
  • temporary fencing, road barriers and signage to provide separation of the construction zone from the public. 

Construction works will require use of the contractor’s temporary site compound on the corner of Wentworth Street and Alexandra Esplanade. This compound will be removed and the area remediated as soon as practical following completion of the works. 

As part of the reinstatement of the site, Bellerive Beach and the sand dune will be reconstructed to match the pre-construction condition. Erosion control matting and new plantings will be installed in the sand dunes and the affected section of the Clarence Foreshore Trail will be reconstructed.   

If you have any questions, please contact City of Clarence – Contact Us. 

 

Hours of Disruption: On-going - Monday to Friday

Disruption Type: Changed traffic, parking, pedestrian conditions

Roads

Backhouse Lane Cambridge – Road upgrade

9 September 2024 - 30 June 2025

Works have begun on the road upgrade of Backhouse Lane Cambridge.

The purpose of these works is to upgrade Backhouse Lane from Kennedy Drive to the turning circle at the end of the road to provide a width and condition suitable to its current use, including the provision of stormwater drainage and a footpath.

Works will commence Monday 9 September 2024 for a period of approximately 30 weeks- weather dependant.

The project will be completed in two stages:

  1. Stage 1 (September 2024) will be in the section between No. 100 Backhouse Lane and the turning head at the end of the lane and includes tree clearing, service locations and trenching for the Telstra and NBN services relocation along the length of Backhouse Lane.
  2. Stage 2 (January 2025) works involve pavement reconstruction adjacent to the Barilla Rivulet bridge (north side).

These works will require a short-term closure of the bridge from 10:00am to 2:00pm, Wednesday 29th January.

Disruption Type: Changed traffic conditions, road closures, bridge closure